Instructions
- Before
base is uncrated, it must be checked for any damage that may have
occurred during transit. John Kramer's
Fabrications, Inc. is not responsible
for any damage that occurs after delivery of base.
- Once
uncrated, base must not be set on any sides, base must be kept
flat and treated like glass.
-
Floor where base is to be installed must be flat and level.
- Make
sure there is enough clearance around drain so strainer nut is
below sub floor.
-
All struts under base must be in contact with floor to maintain
warranty.
- Install
base against studs - use no mechanical fasteners.
- Never
force base between studs. 1/8" clearance is recommended.
- Install
wall material (plywood, moisture resistance drywall, cement board)
at least 1/2" from top of water table on base.
- You
are now ready for finished wall installation.
|
|
|
|